Progress Update 9/13/2019

The following construction progress has been made:

·        Bleachers seats have been installed and are complete.

·        Basketball Goal Installation is complete.

·        Ceiling grid and lights have been complete in sequence 1 and 2

·        Wall Panel Installation is complete.

·        Mechanical System Startup is complete for gym space.