Progress Update 8/02/2019

The following progress has been made:

·        Exterior brick is complete

·        Sidewalks under canopy and front area are complete

·        Sidewalks around south side of the building are complete

·        Parent loop is back open

·        TPO roof is 90% complete

·        Overhead MEP in gym areas are complete

·        Block-fill 90% complete