Progress Update 7/12/2019

The following construction progress has been made:

  • Site utilities installed prior to the new parking lot.

  • Roof leaders installed prior to the parking lot.

  • Curb and gutter are installed.

  • Mechanical Pump house equipment installation is underway.

  • Overhead ceiling rough in for high roof areas underway.

  • Binder has been installed and complete.

  • Pump house exterior mechanical pads poured.

  • TPO roofing is substantially complete.

  • Interior masonry is 90% complete.

  • Brick around 3 sides of the building is complete.