Progress Update 8/02/2019

The following progress has been made:

·        Exterior brick is complete

·        Sidewalks under canopy and front area are complete

·        Sidewalks around south side of the building are complete

·        Parent loop is back open

·        TPO roof is 90% complete

·        Overhead MEP in gym areas are complete

·        Block-fill 90% complete

Progress Update 7/12/2019

The following construction progress has been made:

  • Site utilities installed prior to the new parking lot.

  • Roof leaders installed prior to the parking lot.

  • Curb and gutter are installed.

  • Mechanical Pump house equipment installation is underway.

  • Overhead ceiling rough in for high roof areas underway.

  • Binder has been installed and complete.

  • Pump house exterior mechanical pads poured.

  • TPO roofing is substantially complete.

  • Interior masonry is 90% complete.

  • Brick around 3 sides of the building is complete.

Progress Update 4/26/2019

The following Progress has been made:

·       Large gym joists underway

·       Joists and decking complete for Sequence 1&3

·       Underground storm detention 80% complete

·       Parking lot storm install complete

·       Pump House rough in underway

Progress Update 3/5/2019

The rain insists on sticking around, and so do we. Despite challenges with the weather, progress has been made.

  • Sequence 3 footings completed on 2/27.

  • Final sequence of stem walls begins this week.

  • Slab preparation has started this week.

  • MEP Slab rough will conclude this week.