Progress Update 9/13/2019

The following construction progress has been made:

·        Bleachers seats have been installed and are complete.

·        Basketball Goal Installation is complete.

·        Ceiling grid and lights have been complete in sequence 1 and 2

·        Wall Panel Installation is complete.

·        Mechanical System Startup is complete for gym space.

Progress Update 8/02/2019

The following progress has been made:

·        Exterior brick is complete

·        Sidewalks under canopy and front area are complete

·        Sidewalks around south side of the building are complete

·        Parent loop is back open

·        TPO roof is 90% complete

·        Overhead MEP in gym areas are complete

·        Block-fill 90% complete

Progress Update 7/12/2019

The following construction progress has been made:

  • Site utilities installed prior to the new parking lot.

  • Roof leaders installed prior to the parking lot.

  • Curb and gutter are installed.

  • Mechanical Pump house equipment installation is underway.

  • Overhead ceiling rough in for high roof areas underway.

  • Binder has been installed and complete.

  • Pump house exterior mechanical pads poured.

  • TPO roofing is substantially complete.

  • Interior masonry is 90% complete.

  • Brick around 3 sides of the building is complete.

Progress Update 4/26/2019

The following Progress has been made:

·       Large gym joists underway

·       Joists and decking complete for Sequence 1&3

·       Underground storm detention 80% complete

·       Parking lot storm install complete

·       Pump House rough in underway